CREZ TX T-Line Project
Blattner Energy
227 Miles of a Competitive Renewable Energy Zone (CREZ).
This project routed from north of Abilene to near Corsicana, Texas, and was completed in just 14 months. It included 189 miles of double circuit and 36 miles of single circuit with more than 1,800 tangent and angled concrete and steel poles plus 34 steel poles on caisson foundations.
Achievements: Commitment to Solutions.
Self-performance of key project activities allowed the team to work as a seamless unit to manage production and led to a successful completion of the project.
- Worked with 30 different structure types
- Adapting to a year's worth of rainfall in just 4 months
- Engineering and geotechnical changes